05/10/2018
Anonymous
Installation was quick; completed in one day. There was a delay in getting the county inspection scheduled and then getting the inspection certificate back from the county. After that, it took only a couple of days to get Permission To Operate from the utility company. Finally able to turn the system on about a month after installation. The Project Manager was very helpful in getting through all the red tape and scheduling issues.