12/17/2015
Anonymous
Installation scheduled for 4/9/09 actual starting date was 4/13/09. Solar pv insulation was completed on 4/14/09. Waiting for electrical inspector on 4/23/09 inspector arrived ck and failed insulation. Schedule repairs were scheduled for 5/5/09 finally showed up on5/8/09. Waiting for electrical inspector on 5/11/09 inspector arrived and passed system. Waiting for witness inspection on 5/15/09 utility witness approved. Finally on 5/21/09 UI installed the meters and Diana turned the system on. <br />I requested information and pricing for Sunpower Monitoring System, as of 6/11/09 I have not received any information. With all the aggravation and time wasted on my part waiting for people to show up I should be entitled for some compensation. Especially after the statement you will be up and running in 10 days after the solar pv system was installed. The CCEF also passed